Top Projects 2016

2016 Top Projects Hero

The Vancouver Business Journal’s special Top Projects edition features each year’s most outstanding construction projects. This year’s collection of developments paints a robust and exciting picture of Southwest Washington’s business, transportation and residential growth.

This year’s Top Project is the Cowlitz Indian Tribe’s resort casino, ilani, a 368,000-square-foot facility that will feature 15 restaurants, bars and retail shops; a 100,000-square-foot gaming floor; and event space with seating up to 2,500 guests. Ilani, with a construction cost of $196,000,000, is also the largest commercial project that broke ground this year. The top public works project is the C-Tran Bus Rapid Transit project on Fourth Plain Boulevard. This project, at a construction cost $15,352,230, consists of 33 new bus stops and improvements throughout the most heavily used transit corridor in C-Tran’s system. The largest residential project this year is the second and third phases of Pleasant View Estates in Vancouver, with a total of 206 single family homes to be developed.

Other notable projects include the Sunlight Supply World Headquarters, a $26 million dollar consolidation of the Vancouver company’s facilities; both residential and commercial remodels of various historic buildings at the Fort Vancouver National Site West Barracks; and a zeitgeist of home and apartment building.

Top Projects Submission Guidelines

Top Projects accepts and publishes all commercial, public and residential projects for which a reasonable amount of information can be verified. Projects may be located in Clark, Cowlitz and Skamania counties and must have must have broken ground during the time specified in the year prior to the publication. We strive to maintain the highest level of accuracy, and we do not publish projects for which we cannot personally verify construction cost, general contractor, owner or construction start and end dates. Please visit www.vbjusa.com and click on Breaking Ground to submit your next project or to be sure you are on our email list when we call for submissions. Thank you!

COMMERCIAL PROJECTS

Ilani1. Ilani

RIDGEFIELD

Developed by Salishan-Mohegan LLC in collaboration with the Cowlitz Indian Tribe, ilani will be a premier gaming, dining, entertainment and meeting destination in Southwest Washington when completed in spring 2017. The 368,000-square-foot facility will have 15 restaurants, bars and retail shops; a 100,000-square-foot gaming floor with 2,500 slot machines, 75 table games, a high limit gaming room and VIP Lounge; and event space with seating for up to 2,500 guests.

Construction Cost: $196,000,000 Start Date: 8/31/2015 Completion Date: 5/30/2017

General Contractor: Swinerton Builders

Project Owner: Cowlitz Indian Tribe

Funding Source: Bank of America, Key Bank, Citizens Bank, Columbia Bank, Merrill Lynch

Project Executive: Kara Fox-LaRose, General Manager

Architect: Friedmutter Group

Engineers/Planners: Kittelson & Associates, BergerABAM, Olson Engineering, Keating, Bob Henderson

Subcontractors: America’s Family Diner, Arrow Roofing & Sheet Metal, Barclay Dean Architectural Products, Bassett Construction Inc., Culver Glass Company, Dillon Works, Floor Factors Inc., Friedmutter Group, Goodfellow Bros. Inc., Harder Mechanical Contractors Inc., Interior Woodworking Specialists, Keystone Masonry Inc., KHS&S Contractors Inc., Kittelson & Associates Inc., Mill Plain Electric, National Construction Rentals Inc., On Electric Group Inc., Parametrix Inc., Performance Contracting Inc., Performance Systems Inc., Professional Roof Consultants, Rite-Hite Co. LLC, Safway Services LLC, Sak & Associates Inc., Schonert & Associates Inc., Securitas Security Services USA Inc., Smith & Greene Company, Snyder Roofing of Oregon LLC, Streimer Sheet Metal Works Inc., Thyssenkrupp Elevator, Ulster Carpet Mills (North America) Inc., Viking Automatic Sprinkler Co.

Sunlight Supply2. Sunlight Supply World Headquarters

Vancouver

Sunlight Supply is consolidating its five Southwest Washington Facilities into a single 306,000-square-foot building. The new space will feature 173,000 square feet of warehouse space, 80,000 square feet of office space, 49,000 square feet of manufacturing space, and 4,000 square feet of greenhouse space for testing and research. When complete, Sunlight Supply’s new world headquarters is expected to generate in excess of $17 million in wages and $19 million with local vendors annually.

Construction Cost: $26,000,000 Start Date: 1/11/2016 Completion Date: 2/17/2017

General Contractor: Perlo Construction

Project Owner: Craig Hargreaves

Funding Source: U.S. Bank

Project Executive: Bradley S. Thomas Construction

Engineers/Planners: VLMK Engineering & Design

Subcontractors: Rotschy Inc., Taylor Transport Inc., Cemex, Lakeside Industries, Precision Rebar, Willamette Valley Steel, Aloha Welding, Dennis’ 7 Dees, Mid-Columbia Caulking, Ross Island Sand & Gravel, Alite Construction

Erickson Farms3. Erickson Farms Phase 6

CAMAS

Erickson Farms Phase 6 consists of six commercial buildings located in the Erickson Farms subdivision (known as Village Center) with 25,000 square feet of commercial space and 15,000 square feet of office/ loft space. The total value of the project is $12,000,000.

General Contractor: Rotschy Inc.

Project Owner: Lake Shore Development Corp.

Funding Source: Private

Project Executive: Pat and Mark Jeffries

Architect: Woodblock Architecture

Engineers/Planners: SGA Engineering

Subcontractors: Not provided

New Heights4. New Heights North

BATTLE GROUND

General Contractor: Halbert Construction Services LLC

Project Owner: New Heights Church

Funding Source: Bank of the West

Project Executive: Bryan Halbert

Architect: Walla Architectural Services PLLC

Engineers/Planners: Walla Architectural Services PLLC, Roggenkamp Structural Engineers P.C., Sterling Design Inc.

Subcontractors: Catworks Construction, Lakeside Industries, Hicks Striping, Able Fence, DK Contracting, Hi-Mark Concrete, Em3, Cornerstone Masonry, InstaFab, Hayes Cabinets, Gregg Roofing, Advanced Metal Systems, Mid Columbia Caulking, Steve Broders Company, Jack’s Overhead Door, Anderson Glass, Commercial Interior Contractors, BLAM Specialties, PG Long Floor Covering, NW Endeavors, Painting Perfection, Building Material Specialties, Bargreen Ellingson, Firestop Company, Watercents, Entek Corporation, ADK Electric

Construction Cost: $5,050,720 Start Date: 6/11/2015 Completion Date: 9/9/2016

Kyocera addition5. Kyocera Manufacturing Building Addition

Vancouver

General Contractor: TEAM Construction LLC

Project Owner: Todd McMillan

Funding Source: Kyocera

Project Executive: David Gunsul

Architect: Johansson Architecture

Engineers/Planners: Not provided

Subcontractors: Not provided

Construction Cost: $4,400,000 Start Date: 4/25/2016 Completion Date: 11/15/2016

West Barracks6. Fort Vancouver National Site West Barracks Project

Vancouver

Dental Surgery, Quartermaster, Artillery Barracks

General Contractor: Pease Construction

Project Owner: Fort Vancouver National Trust & City of Vancouver

Funding Source: Washington State Historical Society Grant: $309,000; Reinvestment of Property Operations Revenue, City of Vancouver Bonds

Project Executive: Mike True, President & CEO, Fort Vancouver National Trust & Jan Bader, Program & Policy Development Manager for the City of Vancouver

Architect: Bassetti Architects

Engineers/Planners: Interface Engineering, Catena Engineers

Subcontractors: Piper Mechanical, Jet Electric, Net Compliance Environmental Services

Construction Cost: $4,258,538 Start Date: 2/16/2016 Completion Date: 4/18/2017

Heights OK2 Clubhouse7. Heights O.K.2 Clubhouse

Vancouver

General Contractor: Robertson & Olson Construction Inc.

Project Owner: Boys & Girls Clubs of SW Washington

Funding Source: Funds raised from individuals, businesses, and foundations

Project Executive: Elise Menashe

Architect: LSW Architects PC

Engineers/Planners: Robertson Engineering, Terraza Design LLC, Kramer Gehlen & Associates Inc., MKE & Associates Inc.

Subcontractors: Aloha Welding, American Aluminum, Precision Rebar, Prosteel, ABC Roofing, Able Fence, American Direct, Authority Dock & Door, Brix Paving, Building Material Specialties, C&T Nonstop Masonry, Carpentry Plus, Cascade Electric, Cascade Radon, Cemex Construction Materials, Civilworks NW, Concrete Alternatives, Contract Décor, Contract Flooring Consultants, Delta Fire, Drake’s Striping & Paint, EK Plumbing, Gregory Law Landscape, JB Insulation, M&C Construction, Olson Engineering, Oregon Commercial Paint, Oregon Heating & AC, Portland Sheet Metal Works, Quality Cleaning, Reliable Construction Solutions, River City Glass, Sawtooth Caulking, Sustainable Flooring Solutions, Uncommon Cabinetry, Vancouver Sign, Vibetech Specialties, Columbia West

Construction Cost: $3,796,830 Start Date: 8/3/2015 Completion Date: 4/1/2016

Yu Retail Center8. Yu Retail Center

Vancouver

General Contractor: RSV Building Solutions

Project Owner: John and Grace Yu

Funding Source: Wells Fargo

Project Executive: Betty Kaber, RSV Building Solutions

Architect: LLB Architecture

Engineers/Planners: Olson Engineering

Subcontractors: Nutter Corporation, Stewart Plumbing, JNB Mechanical, Hydrotech Fire Protection, Accurate Electric

Construction Cost: $3,500,000 Start Date: 4/1/2016 Completion Date: 10/1/2016

Seton High School9. Seton Catholic College Preparatory High School

Vancouver

General Contractor: Hinton Development LLC

Project Owner: St. Elizabeth Ann Seton Catholic High School Board of Directors

Funding Source: Columbia Bank and the philanthropic community of Southwest Washington

Project Executive: Tricia Roscoe

Architect: LSW Architects PC

Engineers/Planners: Robertson Engineering P.C., Terraza Design LLC, Kramer Gehlen & Associates Inc., MKE & Associates Inc.

Subcontractors: Alliance Industrial Group, All Star Glass Inc., Best Quality Siding, Brandsen Hardwood Floors, Bridgetown Sales / Construction Specialties, Cascade Casework, Cascade Electric, Ceme, Construction Materials Pacific LLC, CH Beresford Co. Inc., DeaMor Associates Inc., Elmer’s Flag & Banner LLC, Fred Shearer & Sons Inc., Geopier Northwest Inc., GW Deal Inc., Hansen Drilling Co. Inc., Hart Crowser Inc., Hi-Mark Concrete Inc., Interior Tech, Lehner Construction, McDonald & Wetle, Metro-Watch, Michaels Precast Concrete LLC, Minister-Glaeser Surveying Inc., MJS Contracting Inc., Mt. Hood Cleaners & Window Coverings, Northwest Scaffold Service Inc., Nutter Corporation, NW Flooring Solutions, Northwest School Equipment, Pacific Fence and Wire Company

Construction Cost: $3,145,625 Start Date: 9/21/2015 Completion Date: 9/7/2016

Kunze Industrial10. Kunze Industrial

Vancouver

General Contractor: Rotschy Inc.

Project Owner: Rotschy Inc.

Funding Source: Private

Project Executive: Cornell Rotschy Architect: Johansson Architecture PC Engineers/Planners: SGA Engineering

Subcontractors: Not provided

Construction Cost: $2,500,000 Start Date: 5/1/2016 Completion Date: 9/1/2016

Port-of-Camas-Washougal-Building11. Port of Camas-Washougal, Steigerwald Commerce Center, No. 17

Vancouver

General Contractor: TEAM Construction LLC

Project Owner: Port of Camas-Washougal

Funding Source: Not provided

Project Executive: David Ripp

Architect: Johansson Architecture PC

Engineers/Planners: TM Rippey Consulting Engineers, MacKay Sposito, Meier Engineering

Subcontractors: Not provided

Construction Cost: $2,317,287 Start Date: 7/10/2015 Completion Date: 1/27/2016

Westlie Ford12. Westlie Ford

Vancouver

General Contractor: RSV Building Solutions

Project Owner: Ryan Dickerson, Randy Dickerson, Port of Camas-Washougal

Funding Source: Riverview Community Bank

Project Executive: Josh Lingo, RSV Building Solutions

Architect: LLB Architecture

Engineers/Planners: RSV Building Solutions

Subcontractors: Garco Steel Buildings, Pacific Steel Erectors, Stewart Plumbing, Hydrotech Fire Protection, JNB Mechanical, Accurate Electric

Construction Cost: $2,100,000 Start Date: 6/1/2015 Completion Date: 2/1/2016

Crossroads at Mill Plain13. Crossroads at Mill Plain & 164th Avenue

Vancouver

General Contractor: TEAM Construction LLC

Project Owner: MAJ Mill Plain at 164th LLC

Funding Source: Columbia Credit Union

Project Executive: Michael Jenkins

Architect: Tiland/Schmidt

Engineers/Planners: Mackenzie

Subcontractors: Not provided

Construction Cost: $2,000,000 Start Date: 4/19/2016 Completion Date: 7/19/2016

CDK Holdings14. CDK Holdings Building

BATTLE GROUND

General Contractor: Robertson & Olson Construction Inc.

Project Owner: CDK Holdings LLC

Funding Source: First Citizens Bank

Project Executive: Brian Dudley

Architect: Wilson Associates Architects & Planners

Engineers/Planners: AKS Engineering & Forestry

Subcontractors: Not provided

Construction Cost: $1,761,058 Start Date: 10/26/2015 Completion Date: 4/7/2016

SunModo15. SunModo

Vancouver

General Contractor: Jackson Contracting LLC

Project Owner: Tricon Capital LLC

Funding Source: First Citizens Bank

Project Executive: Jackson Contracting LLC

Architect: Planning Solutions

Engineers/Planners: WDY Structural Civil Engineer, Precision Land Services Inc.

Subcontractors: Not provided

Construction Cost: $1,400,000 Start Date: 5/23/2016 Completion Date: 11/30/2016

SeaMar16. Sea Mar Medical Office Building

Vancouver

General Contractor: TEAM Construction LLC

Project Owner: Sea Mar

Funding Source: Sea Mar

Project Executive: David Gunsul

Architect: Bazan Architects

Engineers/Planners: Not provided

Subcontractors: Not provided

Construction Cost: $1,250,000 Start Date: 2/1/2016 Completion Date: 6/30/2016

Dick Hannah Subaru17. Dick Hannah Subaru

Vancouver

General Contractor: Jackson Contracting LLC

Project Owner: Dick Hannah Dealerships

Funding Source: Private

Project Executive: Mark Jackson

Architect: Walla Architectural Services PLLC

Engineers/Planners: Not provided

Subcontractors: Not provided

Construction Cost: $602,000 Start Date: 11/1/2015 Completion Date: 6/15/2016

Pacific Continental Bank18. Pacific Continental Bank Tenant Improvement

Vancouver

General Contractor: TEAM Construction LLC

Project Owner: Pacific Continental Bank

Funding Source: Pacific Continental Bank

Project Executive: Kristy Weaver

Architect: Mackenzie

Engineers/Planners: The Element Group

Subcontractors: Not provided

Construction Cost: $600,000 Start Date: 12/9/2015 Completion Date: 3/21/2016

Windermere Stellar19. Windermere Stellar Tenant Improvement

Vancouver

General Contractor: TEAM Construction LLC

Project Owner: Northwest Equity Holdings Inc.

Funding Source: NWEHI

Project Executive: David Gunsul

Architect: GBD Architects

Engineers/Planners: Not provided

Subcontractors: Not provided

Construction Cost: $444,000 Start Date: 7/27/2015 Completion Date: 9/28/2015

Neurosciences Center20. Thomas and Sandra Young Neurosciences Center

Vancouver

(Renovation of Tower 6)

General Contractor: Swinerton Builders

Project Owner: PeaceHealth Southwest Medical Center

Funding Source: PeaceHealth, Thomas and Sandra Young, community donors

Project Executive: Not provided

Architect: PKA Architects

Subcontractors: Don Frank Floors

Construction Cost: $225,000 Start Date: 7/1/2015 Completion Date: 8/15/2015

PUBLIC WORKS PROJECTS

C Tran Turtle Place1. C-Tran Bus Rapid Transit Fourth Plain Blvd.

Vancouver

Fourth Plain Boulevard is the most heavily used transit corridor in C-TRAN’s system with over 6,000 daily trips that has resulted in a service that is often unreliable and overcrowded. The Vine will implement a modern, enhanced transit line along the Fourth Plain and Fort Vancouver Way corridors between downtown Vancouver and Westfield Vancouver Mall. The project consists of construction of 33 new bus stops, as well as traffic signal, storm, water, sewer and street improvements.

Construction Cost: $15,352,230 Start Date: 10/28/2015 Completion Date: 12/30/2016

General Contractor: Tapani Inc.

Project Owner: C-Tran

Funding Source: FTA, local funds, Regional Mobility Grant, on hand funds

Project Executive: Chuck Green

Architect: Pivot Architecture

Engineers/Planners: Parsons Brinkerhoff, Mackay Sposito, PAE Engineers, Equilibrium LLC, DKS Associates, Mayer Reed

Subcontractors: Mill Plain Electric Inc., Kelaye Concrete LLC, Able Fence Company Inc., C&R Tractor & Landscape Inc., Granite Construction Company, Schonert & Associates Inc., Specialized Pavement Mkg. Inc., Baker Rock Resources, Veva Company LLC dba Vevaco, Sawtooth Caulking Inc., Ferguson Enterprises Inc., TFT Construction Inc., Tapani Trucking, Advanced Metal Systems Inc., Bar M Steel, Park Place Painting

Slow Sand Filter2. Slow Sand Filter Water Treatment Plant

CAMAS

This project constructs a new drinking water treatment plant, including administration building with office, shop and process area; a roughing filter, filter gallery, slow sand filters and associated site improvements.

Construction Cost: $5,799,978 Completion Date: 3/28/2016

General Contractor: Rotschy Inc.

Project Owner: City of Camas

Funding Source: City of Camas

Project Executive: City of Camas

Engineers/Planners: CH2MHILL

Subcontractors: Northeast Electric, SI Contracting Inc., KPF Surveying, C& T Nonstop Masonry Inc., Forest Fuel Collections LLC, McDonald’s Excavating, West Coast Sand and Gravel, Piper Mechanical, MC Interior LLC, MJS contracting Inc., Ralph’s Concrete Pumping Inc., Bar & M Steel Commercial Inc., Taylor Transport, Rubenstein’s Contact Carpet LLC, D&R Masonry Restoration Inc., Affordable Gutter Services, Karvonen Sand and Gravel Inc., Interstate Fence Company

NE 94th Street3. Northeast 94th Avenue, Padden Parkway to 99th Street

CLARK COUNTY

This project widens Northeast 94th Avenue from two lanes to three lanes and constructs bicycle lanes and sidewalks. The work includes intersection improvements at Padden Parkway and Northeast 94th Avenue including new traffic signals. Primary work includes construction of storm water collection treatment systems, sewer lines, water lines, surfacing, cement concrete curb, gutter and sidewalk, pavement markings and associated work.

Construction Cost: $5,609,203 Start Date: 8/31/2015 Completion Date: 7/12/2016

General Contractor: Tapani Inc.

Project Owner: Clark County

Funding Source: Grants from State of Washington and Federal Surface Transportation Program

Project Executive: Bart Arthur

Engineers/Planners: Clark County, Kittelson, HDR Engineering, Hart Crowser

Subcontractors: Hicks Striping and Curbing, Lakeside Industries, C&R Tractor and Landscape, North 40 Fencing, Em3 Concrete, Northeast Electric, Vancouver Paving, Storie and Associates, Palisade Structures, Trademark Plumbing, Hansen Drilling, Kyle Massie Inc., Storie Barrier Corp., Kysar Logging and Tree Service, CSI Construction Services, Brothers Concrete Cutting, North Fork Resources, Tapani Trucking, A&A Drilling, Molecular Inc., Porter W. Yett Co., Bergen Construction, AAA Septic, Dan Jones Conveyor, Ralph’s Concrete Pumping

PCW Waterfront4. Port of Camas-Washougal Waterfront

WASHOUGAL

Water Access and Waterfront Trail

General Contractor: Tapani Inc.

Project Owner: Port of Camas-Washougal

Funding Source: Port of Camas Washougal

Project Executive: Jeramy Wilcox

Architect: BergerABAM

Engineers/Planners: BergerABAM

Construction Cost: $2,115,389 Start Date: 2/1/2016 Completion Date: 8/12/2016

Port of Vancouver Terminal 45. Port of Vancouver Terminal No. 4

Vancouver

Stage 2 Improvements Project

General Contractor: Rotschy Inc.

Project Owner: Port of Vancouver

Funding Source: Port of Vancouver

Project Executive: Todd Coleman

Architect: N/A

Engineers/Planners: HDJ Design Group, PLLC

Subcontractors: Northeast Electric, Northern Land Surveying, Hildebrand Concrete, North 40 Fencing, Lakeside Paving, Drake’s Striping & Paint, Jammie’s Environmental, McDonald’s Excavating, Diamond Concrete Cutting

Construction Cost: $1,687,985 Start Date: 2/9/2016 Completion Date: 7/8/2016

RESIDENTIAL ESTATES

Pleasant View Estates1. Pleasant View Estates Phases 2 & 3

Vancouver

This project site consists of five tax lots totaling about 88 acres of planned residential development. Sitework included grading the site for residential lots with associated streets, underground utilities and water facilities. A total of 206 lots are planned for this site.

Construction Cost: $43,500,000 Start Date: 9/17/2015 Completion Date: 5/27/2016

General Contractor: Lennar Northwest Inc., Rotschy Inc. (sitework)

Project Owner: Lennar Northwest Inc.

Funding Source: Lennar Northwest Inc.

Project Executive: Lennar Northwest Inc.

Architect: Not provided

Engineers/Planners: SGA Engineering, PLLC, Ecological Land Services, GeoPacific Engineerging, Archeological Services

Subcontractors (sitework): Able Fence Company, C&R Tractor, Em3 Concrete, Karvonen Sand and Gravel, Prairie Electric

Lacamas Prairie2. Lacamas Prairie Estates

Vancouver

The property is roughly 80 acres to be developed into 176 lots for single family homes. Project development will also include storm water detention facilities, new streets, underground utilities, trails and landscaped areas.

Construction Cost: $34,000,000 Start Date: 9/1/2015 Completion Date: 6/30/2016

General Contractor: Lennar Northwest Inc., Rotschy Inc. (sitework)

Project Owner: Lennar Northwest Inc.

Funding Source: Lennar Northwest Inc.

Project Executive: Lennar Northwest Inc.

Architect: Not provided

Engineers/Planners: AKS Engineering and Forestry LLC

Subcontractors (sitework): C& R Tractor, Em3 Concrete, Granite Construction, North 40 Fencing

Alder Pointe3. Alder Pointe Apartments

BATTLE GROUND

Alder Pointe Apartments is a 180-unit development located in Battle Ground, Wash. The complex contains three-story buildings with 24 units each; two-story buildings with garages below second-floor apartments; and dedicated garage buildings. Residents will have access to a central clubhouse housing a community room, a meeting room, a fitness center and an outdoor pool. The buildings are separated by ample landscaped areas with walking paths and a play structure to provide a park-like setting for residents.

General Contractor: TEAM Construction LLC

Project Owner: Principal Properties LLC

Funding Source: Northwest Bank

Project Executive: TJ Fontenette

Architect: LSW Architects PC

Engineers/Planners: Olson Engineering Inc., Terraza Design LLC, Harper Houf Peterson Righellis Inc., Cascade Radon, Sandy Van Dorn Design, R&W Engineering Inc., TEAM Construction, Scott Erstad Design + Illustration

Subcontractors: Not provided

StoneBriar4. Stonebriar Subdivision

Vancouver

General Contractor: Tapani Inc. & Pacific Lifestyle Homes

Project Owner: Evergreen Quarry LLC

Funding Source: Private

Project Executive: Kevin Tapani

Architect: Not provided

Engineers/Planners: SGA Engineering

Subcontractors: Not provided

Construction Cost: $10,875,000 Start Date: 6/1/2015 Completion Date: 1/29/2016

Isabella Court5. Isabella Court Apartments

Vancouver

General Contractor: TEAM Construction LLC

Project Owner: REACH Community Development

Funding Source: HUD, State and Federal tax Dollars

Project Executive: Ben Sturtz

Architect: MWA

Engineers/Planners: WRK Engineers

Construction Cost: $7,500,000 Start Date: 12/7/2015 Completion Date: 12/1/2016

Lincoln Place6. Lincoln Place Apartments

Vancouver

General Contractor: TEAM Construction LLC

Project Owner: Vancouver Housing Authority

Funding Source: VHA, HUD, State and Federal Tax Dollars

Project Executive: Jim Davis

Architect: MWA

Engineers/Planners: WRK Engineers

Construction Cost: $3,900,000 Start Date: 6/6/2015 Completion Date: 1/28/2016

Canterbury Trails Subdivision7. Canterbury Trails Subdivision Sitework

RIDGEFIELD

General Contractor: Rotschy Inc.

Project Owner: Canterbury Trails JU LLC

Funding Source: Canterbury Trails LLC

Project Executive: Not provided

Architect: N/A

Engineers/Planners: PLS Engineering

Subcontractors: Em3 Concrete, Lakeside Inc., Prairie Electric

Construction Cost: $2,200,000 Start Date: 6/8/2015 Completion Date: 1/28/2016

West Barracks Remodel8. Fort Vancouver National Site West Barracks Project

Vancouver

Infantry Barracks

General Contractor: Pease Construction

Project Owner: Fort Vancouver National Trust & City of Vancouver

Funding Source: $1 million from the State of Washington, Reinvestment of Property Operations Revenue, City of Vancouver Bonds

Project Executive: Mike True, President & CEO, Fort Vancouver National Trust & Jan Bader, Program & Policy Development Manager for the City of Vancouver

Architect: Bassetti Architects

Engineers/Planners: Interface Engineering, Catena Engineers

Subcontractors: Piper Mechanical, Jet Electric, Net Compliance Environmental Services

Construction Cost: $2,174,248 Start Date: 2/16/2016 Completion Date: 4/18/2017